Ford APTL Tower Demolition
Industrial Strip-Out | Allen Park, Michigan
Selective Dismantling Within an Active Automotive Testing Facility
NADC performed the selective dismantling of six 86-foot-tall carousels at Ford Motor Company's Allen Park Test Laboratory in Allen Park, Michigan.
The project involved removing large industrial testing equipment and associated structural components within an active facility where testing operations continued around the clock. Demolition activities required careful coordination, specialized equipment and extensive safety controls to protect surrounding infrastructure and prevent disruptions to ongoing operations.
Project Snapshot
Scope of Work
Selective demolition and dismantling of six 86-foot-tall automotive testing carousels within an approximately 5,000-square-foot work area, including associated tower components and equipment.
Project Conditions
Demolition within an active automotive testing laboratory operating 24 hours a day, seven days a week. Work required coordination around ongoing testing activities, existing utilities, limited material staging space and controlled ventilation requirements.
Services Performed
- Industrial Strip-Out
- Selective Demolition
- Equipment Dismantling
- Structural Component Removal
- Material Handling & Removal
- Dust & Ventilation Control
Market
The Challenge
The Ford Allen Park Test Laboratory required the removal of six large automotive testing carousels, each approximately 86 feet tall, within an operational testing environment.
The facility continued testing activities throughout the project, requiring NADC to perform demolition without interfering with surrounding operations or existing building systems. Limited material staging space, elevated work areas and extensive structural components added complexity to the dismantling process.
Additional challenges included maintaining appropriate ventilation and negative-pressure conditions for cutting operations, protecting existing mechanical and electrical systems, and coordinating work within an active industrial facility.
NADC’s Approach
NADC developed a controlled dismantling sequence to safely remove the six carousel systems and associated components.
Rather than relying entirely on chain falls to remove individual car carriers and sleds, NADC identified a safer and more efficient approach by operating the existing carousel mechanisms. This allowed the team to cycle individual carriers into position for removal, reducing hazards associated with conventional lifting methods.
NADC also coordinated with other project contractors to establish appropriate ventilation and negative-pressure conditions before cutting operations began. Work areas were managed with dust controls, fire-watch procedures and protections for surrounding facility operations.
The project involved approximately 4,048 work hours and was completed with zero reported safety incidents.