Shiras Steam Plant Demolition
Power Plant Demolition | Marquette, Michigan
Total Demolition of a Coal-Fired Power Plant
NADC served as the prime contractor for the demolition of the former Shiras Steam Plant in Marquette, Michigan, owned by the Marquette Board of Light & Power.
The project included environmental remediation and total demolition of a three-unit, 77.5 MW coal-fired power plant, three baghouses, an intake structure, two chimneys and supporting infrastructure across an approximately 10-acre site along Lake Superior.
Project Snapshot
Scope of Work
Environmental remediation and demolition of approximately 106,725 square feet of power generation facilities, including the main powerhouse, three baghouses, intake structure, coal-handling equipment and two chimneys measuring 358 and 250 feet in height.
Project Conditions
Demolition adjacent to Lake Superior, with an intake structure and 358-foot chimney located approximately 50 feet from the shoreline. Additional challenges included removing coal conveyor sections positioned directly above an active electrical switchyard.
Services Performed
- Environmental Abatement
- Total Demolition
- Industrial Dismantling
- Critical Lift & Pick
- Equipment Removal
- Site Preparation
Market
The Challenge
The former Shiras Steam Plant contained three coal-fired boilers, three turbines, three condensers, coal bunkers and extensive process piping and equipment.
The waterfront location presented unique demolition challenges, particularly the removal of the 358-foot chimney and intake structure situated approximately 50 feet from Lake Superior. Coal conveyor sections located directly above an active electrical switchyard required carefully engineered lifting operations to protect surrounding infrastructure.
Environmental remediation was also required before demolition, including asbestos, universal waste, lead-impacted paint and PCB-impacted concrete.
NADC’s Approach
NADC coordinated environmental remediation and abatement activities before proceeding with the demolition of the powerhouse and supporting structures. The asbestos and lead abatement of the powerhouse and support buildings was completed ahead of schedule.
Demolition operations included removal of the two chimneys, three baghouses, intake structure and associated power generation equipment. NADC also performed engineered crane lifts to safely remove coal conveyor sections positioned above the active switchyard.
All building demolition activities were completed on schedule, with more than 26,000 work hours performed and zero reported safety incidents or injuries.